The Firm
IMPERIAL COMPANY LLC
RUB 85,000,000
The parties settled their mutual claims and concluded the court proceedings by approving a settlement agreement. Case No. А40-151517/2024
Case Overview:
A claim in the amount of approximately 86 million rubles was filed against the client. The proceedings were terminated after the parties’ settlement agreement was approved on November 22, 2024.
Scope of Services
ALPERIYA PARTNERS provided full support in executing the settlement agreement between the parties, drafting a settlement that eliminated all risks and fully met the client’s interests, negotiating the key provisions of the draft with the plaintiff, and securing its approval in court.
Significance and Results for the Client
Recovery from the client of the principal debt and penalties under several shared construction participation agreements (DDUs) totaling over 85 million rubles would have resulted in the client’s insolvency and a complete halt of commercial operations.
The final outcome ensured the mutual satisfaction of both parties’ interests, resulting in the termination of the shared construction participation agreements (DDUs) along with the cessation of all related obligations and mutual claims, leaving the client with only a new obligation to reimburse 30% of the state fee for consideration of the claim (60,000 rubles).